How to unassign a Work order operation (WOO) from a Production resource group (REGCONFIG)
From the Distribute work order operations from resource group to member resources (DWOO) application.
Click the Production resource group drop-down menu, found in the Distribute work order operations from resource group to member resources area.
In the Production resource group list, select, or search for the intended Production resource group (REC) containing the Production resource (RESCONFIG) member, which is assigned the Work order operation (WOO), you want to unassign,
From the Member resources area, click the Production resource (RESCONFIG) member you want to unassign the Work order operation (WOO).
With the Production resource (RESCONFIG) member selected in the Member resources area, locate the intended Work order operation (WOO) in the Member resource work order operation area by either selecting or searching.
Click on the Remove work order operation assignment icon in the Unassign column.
The unassigned Work order operation (WOO) will now be placed back in the Work roder operations area list. Currently unassigned.
Note
To unassign a Work order operation (WOO), it can not be active. Therefore only Work order operations (WOO) in Status 2 (In queue) or Status 3 (Ready), can be unassigned.