Setting name

Description

Cost deviation control in Production

Value in this setting is either Amount or PCT (percent). On complete operation - If total logged operation costs differs from Planned operation costs, - an alert will be set on the operation according to the percent or amount in the setting  ProductionCostDeviationValue

DayLimit for Recalculation of Work Order cost based on Changes

This setting sets the limit for which planned productions that should be recalculated when changes are done to materials that the production is linked to. The value in this setting is the max number of days ahead production is planned and still will be recalculated immediately when material cost is changed. Setting has a default value of 30 days.

Value for cost deviation control in Production

Value in this setting is an Amount or a Percent. When operation is  completed - If total logged operation cost differs from Planned operation cost, - an alert will be set on the operation according to the value in this setting

Work Log Deviation Lower Limit Percentage

Value in this setting is a percentage. On complete operation - If total logged operation time differs from Planned operation time, an alert will be set on the operation according to the percentage in this setting

Work Log Deviation Upper Limit Percentage

Value in this setting is a percentage. On complete operation - If total logged operation time differs from Planned operation time, an alert will be set on the operation according to the percentage set in this setting