Load Production resources (RESCONFIG) - INP/73367
This load will not update existing Production resources (RESCONFIG).
Possible fields to be loaded into RamBase are listed in the Field column in the following table. The other columns in this table provide additional information about each field.
Field | Required | Length | Example | Description |
NAME | Y | Name of Production resource (RESCONFIG). | ||
ST | Y | 4 | Status. Must be 1 or 4. | |
CLASS | Y | V | Production resource (RESCONFIG) class. | |
CATEGORY | Y | SINGLE | Production resource (RESCONFIG) category. Legal values are SINGLE, MEMBER or GROUP. | |
SHORTNAME | Short name of Production resource (RESCONFIG). | |||
EXTID | Production resource (RESCONFIG) external system id. | |||
NOTE | Description of the Production resource (RESCONFIG). | |||
GROUPID | Production resource (RESCONFIG) group id. | |||
ASSIGNTORESTRICTEDSTOCKLOCATIONS | 1 | Set value 1, if the Production resource (RESCONFIG) should be assigned to restricted stock locations. | ||
ALLOWGROUPING | 1 | Set value 1, to allow resource to use work order operation grouping. | ||
ALLOWMANHOURS | 1 | Set value 1, if man hours can be added to the the work log of work order operations. | ||
ALLOWMULTIOPERATOR | 1 | Set value 1, if multiple operators can work with one work order operation. | ||
HOURRATEPRE | 100 | Rate per hour for operations setup step, given in system currency. | ||
HOURRATE | 100 | Rate per hour for operations step, given in system currency. | ||
HOURRATEPOST | 100 | Rate per hour for operations post step, given in system currency. | ||
CALCULATECOSTBYPLANNEDHOURS | 1 | Set value 1 = Operation cost is calculated based on planned operation hours. Blank (Default) Operation cost is calculated by logged hours. |