This load will not update existing Production operations (OPR).

Possible fields to be loaded into RamBase are listed in the Field column in the following table. The other columns in this table provide additional information about each field.

Field

Required

Length

Example

Description

OPERATION

Y

Name of the Production operation (OPR).

OPCLASS

Y

Production operation class.

OPTIME

Y*

1.5

Planned run time in hours for the Production operation (OPR). 1h 30min is given as 1.5. * Either OPTIME or OPPRETIME must be specified.

OPPRETIME

Y*

1.5

Planned setup time in hours for the Production operation (OPR). 1h 30min is given as 1.5. * Either OPTIME or OPPRETIME must be specified.

OPPOSTTIME

1.5

Planned cleanup time in hours for the Production operation (OPR). 1h 30min is given as 1.5.

RESEXTID

Y**

Resource (RES) id in the external system. ** Either RESOURCENO (100000) or RESEXTID must be included.

RESOURCENO

Y**

100000

Resource (RES) id in RamBase. ** Either RESOURCENO (100000) or RESEXTID must be included.

EXTID

The Production operation (OPR) external system id.

DESCRIPTION

Description of the Production operation (OPR).

PICKINGMUSTBECOMPLETED

1

Set value 1, if picking must be completed. Then all parts for this and previous operations must be picked before current operation can be completed.

HASCHECKPOINT

1

Set value 1, if the Production operation (OPR) has a checkpoint set.

CHECKPOINTDESCRIPTION

Checkpoint description.

CHECKSERIALNOONPARTS

1

Set value 1, if it require serial number before completion. Then all items in the tracelist for all product units needs to have serial number assigned.